Prepare an organizational chart depicting the construction process. Identify the parties involved, their functions, responsibilities, and connections with each other.
An
organizational chart depicting the construction process is shown below.
ID
|
Task
name
|
Duration
|
Start
|
Finish
|
1
|
Start
|
0 days
|
Mon 6/24/13
|
Mon 6/24/13
|
2
|
Mobilize
|
10 days
|
Mon 6/30/13
|
Wed 7/10/13
|
3
|
Site Storm Drainage
|
44 days
|
Mon 7/1/13
|
Tue 8/13/13
|
4
|
Site Water Lines
|
20 days
|
Mon 7/1/13
|
Fri 7/19/13
|
5
|
Site Sanitary Lines
|
15 days
|
Mon 7/1/13
|
Mon 7/15/13
|
6
|
Clear/Cut/Strip Site
|
15 days
|
Mon 7/1/13
|
Mon 7/15/13
|
7
|
Survey & Layout
|
15 days
|
Mon 7/1/13
|
Mon 7/15/13
|
8
|
Rebar Drawings &
Fabrication
|
20 days
|
Mon 6/30/13
|
|
9
|
Structural Steel Drawings
|
35 days
|
Mon 6/30/13
|
Mon 8/5/13
|
10
|
Excavation
|
10 days
|
Fri 7/26/13
|
Mon 8/5/13
|
11
|
Foundation Forms
|
15 days
|
Thu 8/8/13
|
Thu 8/22/13
|
12
|
Foundation Rebar, Foundation concrete
|
10 days
|
Thu 8/8/13
|
Sat 8/17/13
|
13
|
Structural steel fabrication
|
40 days
|
Thu 8/8/13
|
Wed 9/18/13
|
14
|
Backfill
|
10 days
|
Wed 9/18/13
|
Fri 9/27/13
|
15
|
Deliver steel
|
1 day
|
Fri 9/27/13
|
Fri 9/27/13
|
16
|
Steel Erection
|
24 days
|
Fri 9/27/13
|
Mon 10/21/13
|
17
|
Metal decking
|
5 days
|
Wed 10/23/13
|
Mon 10/28/13
|
18
|
Frame/Insulate/Sheath Lower
|
10 days
|
Fri 11/1/13
|
Mon 11/11/13
|
19
|
Frame/Insulate/Sheath/Upper
|
45 days
|
Mon 11/11/13
|
Mon 12/23/13
|
20
|
Winter Shutdown
|
0 days
|
Last Day
|
Last Day
|
The
Parties involved in the construction process are,
·
Owner
·
Design Professional
·
Contractors
·
Material Supplier
·
Inspectors
Functions,
Responsibilities and Connections with each other are discussed below.
The construction process is like
a chain reaction where all the parties should be connected with everyone
involved in the process.
Owner:
The initiator of the project is called as owner. He is the responsible to
arrange the finances necessary for the constructions. After arranging the
complete finances for the process the owner should then link with the design
professionals who will do all the designs, specifications, layouts and so on.
Designer
Professionals: He is responsible for the project.
Architect or a designer should show the entire output of the building to the
contractor and the owner. Each specifications should be made clearly. And the
role of designer is not completed with the designing process. During the
construction he should inspect the building is that their specifications are
done properly.
Contractor:
After finishing the design process a owner should go to the contract part where
the full estimation of the process is made and kept for bidding or negotiating
for the owner. Here lump sum process is widely used for the private project.
After making the contract agreement the complete estimation of the work should
be submitted to the designer for approval.
Material
Supplier: If any materials are specified by the
contractor on the site the perfect layout, shop drawings, and material
specification should be given to the contractor from the supplier or vendors.
Those materials should be submitted to the designers for the approval.
Inspectors:
During the construction process a owner can go with the private agent or
inspectors who can visit the building and do some laboratory and field test for
the materials used on the job site.